Answer:
$60,000
Explanation:
The amount of overheads which shall be allocated to the three projects shall be determined using the following mentioned formula:
Overhead amount=overhead rate* direct labor costs
In the given question
overhead rate=60%
direct labor costs=$100,000
Overhead amount=60%*100,000
               =$60,000