Respuesta :
Answer:
a) EOQ ≈ 250
b) POQ = 1.59 ≈ 2 months
c) Cost of EOQ = 1275 USD
  Cost of POQ = 937.5 USD
Explanation:
Again, the essential data is not provided in this question but I have found this question on internet and I will share the required data here in this solution:
a) EOQ = Economic Order Quantity:
FIrst of all, we have to calculate EOQ and for that we have following formula:
Holding Cost = 0.75
Setup Cost = 150
So, here's the required data which is missing in the question:
Month         1     2    3     4     5     6    7
Requirement  100   150   200   150   100   150   250
Now, we are good to go:
So, from the above data we will calculate the Demand:
Demand (D) = Sum of requirement / Total Time Period
D = 100 + 150 + 200 + 150 + 100 + 150 + 250/ 7
D = 157.14
Formula for EOQ:
EOQ = [tex]\sqrt{\frac{2SD}{H} }[/tex]
S = Setup Cost = 150
D= Demand = 157.14
H = Holding Cost = 0.75
Let's plug in the values:
EOQ = [tex]\sqrt{\frac{2*150*157.14}{0.75} }[/tex]
EOQ = 250.71
EOQ ≈ 250
So, the economic order quantity for the above given data is 250 units.
b) POQ = Periodic Order Quantity
Periodic Order Quantity = Economic Order Quantity/ Demand
POQ = 250/157.14
POQ = 1.59 ≈ 2 months
Now, as we have both POQ and EOQ at hand. Next step is to calculate the cost of each plan as mentioned in the question. For which we need MRP of each plan.
1. Cost of Economic Order Quantity:
First of all let me write down the MRP = Materials Requirement Planning Data for EOQ:
Requirement  100   150   200   150   100   150   250
Available      0    150    0     50   150   50   150
Ordered      250   0    250   250   0    250   250 Â
End Inventory  150   0    50   150   50    150   150   700
Now, Let's Calculate the Cost of EOQ:
Setup Cost = Number of Orders x Setup Cost Given
Setup Cost = Â 5 x 150
Setup Cost = 750 USD
Holding Cost = Holding Cost per item given x Number of Inventory held
Holding Cost = 0.75 x 700
Holding Cost = 525 USD
Now, Calculate the Total Cost of EOQ:
Total Cost of EOQ = Setup Cost + Holding Cost
Total Cost of EOQ = 750 + 525
Totol Cost of EOQ = 1275 USD
2. Cost of POQ:
Similarly, we have to calculate the Cost of POQ. For that, we need MRP of POQ as well:
MRP for POQ:
Requirement  100   150   200   150   100    150    250
Available      0    150    0    150    0      150    0
Ordered      250   0    350    0     250    0    250 Â
End Inventory  150   0    150    0      150    0     0      450
Setup Cost = Number of Orders x Setup Cost Given
Setup Cost = Â 4 x 150
Setup Cost = 600 USD
Holding Cost = Holding Cost per item given x Number of Inventory held
Holding Cost = 0.75 x 450
Holding Cost = 337.5 USD
Total Cost of EOQ = Setup Cost + Holding Cost
Total Cost of EOQ = 600 + 337.5
Totol Cost of EOQ = 937.5 USD