The maximum amount of time before a project costs more is 25 days. The project's ideal cost-time schedule is 25 days at a cost of $540.
Total direct cost 330+50= 380
Total indirect cost 180
Total incentives 2x10 = $ 20
Total cost 380+180-20=$540
In project management, all implicit expenses associated with a project are referred to as indirect costs. Another name for indirect costs is burden costs or overhead costs. Other names for indirect costs, sometimes known as burden costs, are factory overhead, manufacturing burden, indirect production expenses, and labour burden. Support expenditures that are not directly connected to a project's activities are known as indirect costs.
Costs that cannot be immediately linked to a cost object are known as indirect costs (such as a particular project, facility, function or product). You can have fixed or variable indirect charges. Expenses for administration, personnel, and security are examples of indirect costs. These are expenses that have nothing to do with manufacturing. Overhead may be a part of some indirect costs. Some overhead expenses, however, are direct costs that can be clearly linked to a project.
To know more about Indirect Project cost visit:
https://brainly.com/question/18566949
#SPJ4